Willen House

Location:
London.

Date:
July 2025.

Client:
Red Construction

Overview

Willen House has being transformed through major structural alterations, including portal frame floor additions, rear tower extensions, and additional levels. The scheme comprises self-contained bedrooms, alongside communal amenities such as sunken gardens, a lounge, a cinema room, a gym, and a yoga studio.

Working alongside the architect, RED Construction and Geostaff France, Fire and Smoke Solutions was brought in to deliver a compliant, low-impact solution within a tight programme for the mechanical smoke extract shafts.

Objectives

  • Replace several non compliant Shaft Wall Smoke Shafts with a Certified Solution.
  • Minimise disruption to surrounding works and live site operations.
  • Complete works on site within 8 weeks.

Challenges:

  • Limited riser space with competing services (electrical and mechanical).
  • Requirement for full compliance with EN 1366-8 and EN 13501-4.
  • Tight construction programme with limited access around shafts.
  • Sustainability targets set by the client requiring recyclable materials.

Our Solution

The FASS GEOTEC® smoke shaft system was specified and installed. GEOTEC® S45 boards were delivered flat-pack, pre-cut to size, and installed using the glue + screw GEOCOL® system. The self-supporting duct allowed installation from inside-out without the need for access all round, saving time and avoiding coordination clashes with other trades.

Our scope covered

  • Design and specification: Ensuring the system met project needs.
  • Procurement: Securing the required materials ahead of schedule to accelerate delivery.
  • Installation: Delivering the works safely and with minimal disruption to the existing site.

Key Outcomes

  • Design and Procurement ahead of schedule: Product secured and installed quicker than planned.
  • Fast installation: On-site works completed in just three weeks.
  • Fully compliant: System met all fire performance and regulatory requirements.

Result

  • Reduced installation time compared with builders work or plasterboard alternatives.
  • No additional site insulation required, saving labour and avoiding error risk.
  • Compact system allowed efficient use of risers, leaving space for other services.

Standards & Compliance Achieved:

  • Tested to EN 1366-8
  • Classified to EN 13501-4 (up to 1500Pa service pressure)
  • IFC Certified (SDI 19 & 20) for smoke shafts and ductwork
  • A1 non-combustible classification (EN 13501-1)
  • ETA 18/0343 – European Technical Assessment