Overview

As part of a wider upgrade at a central London site, Migard needed to improve fire protection for a primary power supply route. The project required the over cladding of the existing cable trenches with an EI120 construction, with minimal disruption to ongoing site activity.

Working alongside the architect and Geostaff France, Fire and Smoke Solutions was brought in to deliver a compliant, low-impact solution within a tight programme.

Objectives

  • Increase the fire protection
  • Minimise disruption to surrounding works and live site operations
  • Complete works on site within 3 weeks

Our Solution

To meet the brief, we installed a Geotec Service Duct using Geostaff’s S45 board system – a proven solution for high-performance fire protection in service installation to BS EN 1366-8 and classified to BS EN 13501-5.

Our scope covered:

  • Design and specification: Ensuring the system met project needs
  • Procurement: Securing the required materials ahead of schedule to accelerate delivery
  • Installation: Delivering the works safely and with minimal disruption to the existing site

Key Outcomes

  • Design and Procurement ahead of schedule: Product secured and installed quicker than planned
  • Fast installation: On-site works completed in just two weeks
  • Fully compliant: System met all fire performance and regulatory requirements

Result

Project Uno was completed ahead of time and with no disruption to other site operations. The installed system delivered the required fire protection performance, and our team managed the process from start to finish – efficiently, safely, and in full compliance with standards.